Verizon’s proposed 5G mini cell towers
A neighbors guide to cell towers in Congress Park
Hi neighbors! If you are concerned about a proposed 5G cell tower near you, our personal experience with Verizon may be helpful. Verizon proposed a mini cell tower at the corner of our home. We live in a duplex, and Verizon sent a letter only to our duplex neighbor. Their policy is that they only notify the directly adjacent property owners (unless the proposed tower is within 5 ft. of a property line). We viewed the City’s guidelines (copied below) for these mini cell towers and realized that the proposed tower was within 15 ft. of a tree. The tree happened to be planted by the City, so we contacted Public Works (email Denver.PWERA@denvergov.org and they will put you in touch with the right person). Public Works gave us this link, where you can find all associated 5G mini cell tower project documents on their E-Review website: https://www.denvergov.org/content/denvergov/en/right-of-way-services/engineering-regulatory-analytics/engineering-plan-review/electronic-review.html
On this website, you will need to review the project documents for the specific tower application near you. It is unclear which folder to click on because the applications are processed in batches. You can find which folder to look through by contacting Public Works and giving them the address of the proposed cell tower. Look at the project documents to see if there is a conflict with the City’s Guidelines or another error. The project documents include referral comments from applicable City Departments and construction plans and drawings (i.e., they send the applications to all the City Departments who have some input on the issue and they make comments).
For us, we identified who the City Forester was who reviewed the application, and contacted that person directly to let them know that there was a tree within 15 ft. of the proposed tower. We realized that the plans/photos of homes Verizon and Public Works are using to do permitting were at least two years old.
There are two reviews–an initial review and then a final review. The City Forester has indicated that the site needs to be moved and this is being taken into account in the final review.
The take-away:
1. Trees make a difference.
2. It is important to follow-up with Public Works if you notice any violation of the City’s Guidelines (copied below).
3. Be in communication with the neighbors who are directly adjacent to the proposed tower, because they are the only ones receiving communication from Verizon.
Please let me know if you have any questions about this process. My email address is alison.philli@gmail.com.
Sincerely,
Alison Sheesley
CITY GUIDELINES
All proposed Freestanding Small Cell Infrastructure shall be located:
A) in no manner or location that obstructs, impedes, or hinders the usual pedestrian or vehicular travel, affects public safety, obstructs the legal access to or use of the public right-of-way, violates applicable law, violates or conflicts with public ROW design standards, specifications, or design district requirements, violates the federal Americans With Disabilities Act of 1990, or in any way creates a risk to public health, safety, or welfare, and;
B) to comply with the current version of the City and County of Denver Small Cell Infrastructure Design Guidelines, and;
C) preferably closest to the corner of two intersecting streets (outside of Signal Equipment clear zones), within alleyways where feasible, or closest to the common side yard property line between adjacent adjoining properties, and;
D) so as not to be located between the perpendicular extension of the primary street-facing wall plane of any single or two-family residential structure and the adjacent street centerline, and;
E) so as not to be located within two hundred fifty feet (250’) from any other Freestanding Small Cell Infrastructure (not including Xcel Energy locations), and;
F) so as not to be located along the frontage of properties designated as Federal, State or Local Historic Landmarks unless otherwise approved by the City and County of Denver, and;
G) so as not to be located along the frontage of City public Parklands (not including Xcel Energy Locations) unless otherwise approved by the City and County of Denver, and;
H) so as not to be located in a manner that otherwise obstructs an adjacent property from reasonably accessing ROW in a manner consistent with the purpose or designated access of said adjacent property, and;
I) so as to not significantly create a new obstruction to primary and inherently valuable sightline(s) of an adjacent property, (for example, if proposed equipment is located between the front living room windows of a residence and a mountain view plane, or directly between an outdoor restaurant dining area and adjacent parkland), and;
J) preferably within the street amenity zone and generally in alignment with existing street trees or utility/ street light poles, if present, and so that no part of proposed foundation is within 1.5 feet from the back of street curb, and;
K) generally placed equidistant between street trees, with a minimum separation of 15 feet (or beyond mature drip line, whichever dimension is greater) from center of tree to pole so that no proposed disturbance is within the critical root zone of any tree, and;
L) no closer than 5 feet from any low-pressure natural gas line, or 15 feet from any intermediate or high-pressure natural gas line, as can be required by Xcel Energy.
IMPORTANT REFERENCE MATERIAL ADDED 7-26-2019
Referenced in Updated Cell Tower Guidelines Page 5