Jackson Street from 6th Avenue to 13th Avenue Water Main Replacement
This project will start Nov 20 2019 and is anticipated to take 5 mo to complete.
Denver Water is going to be replacing a water main and any identified customer-owned lead service lines on Jackson Street starting at 13th Avenue, working south toward 6th Avenue. This project will be completed in two block increments to minimize overall neighborhood impacts; however, neighbors should expect inconveniences including on-site storage of Denver Water’s heavy equipment and materials, road closures, detours, and parking restrictions in the immediate area. This project will take approximately five months to complete and will include the following phases of work:
1. Roto-milling or saw cutting the trench
2. Water main installation
3. Service line replacements and changeovers to the new water main
4. Paving and restoration
The water Denver Water delivers is lead-free, but lead can get into water as it moves through customer-owned water service lines if those service lines contain lead. As part of this water main replacement project, Denver Water will identify and remove any customer-owned water service lines that contain lead and will replace them with new copper water service lines, at no direct cost to the property owner. We will also coordinate and schedule water service line replacements directly with each impacted property owner.
A map of the project can be found at: https://www.denverwater.org/project-updates/pipe-replacement
Denver Water monitors Nextdoor during normal business hours and is committed to responding in a timely manner. Please note that we cannot see any Nextdoor posts other than those we originate. If you have questions or if you want to verify or update your contact information with Denver Water, please call Denver Water Customer Care at 303-893-2444 (7:30 a.m. – 5:30 p.m., Monday – Friday). If you are experiencing a water emergency please call 303-628-6801.